Project Cost

What will the project cost for me?

  • What people pay depends on the following:
    • District Share of the Project cost
    • Interest Rate and Term of Loan
    • Town the person lives in
    • Number of students in the town
    • Property value

What will the total project cost be?

  • In July 2018, when the 7-12 new construction option was chosen as the preferred option the estimated project cost was $155.4 million.
  • The total project cost is now estimated at $146.3 million.  This was determined during the Schematic Design phase and was submitted to the MSBA on February 20, 2019.
  • This represents a $9.1 million dollar reduction in cost.

Eligible vs Ineligible Costs

  • We know the MSBA reimbursement is about 52.89% for any ELIGIBLE expenses.
  • What is an ineligible cost? There are a number of things in the project that are not eligible for reimbursement or exceed the minimum eligibility caps. For example, site costs over 8% are not eligible.
  • We are estimating an approximation of about 40% realized reimbursement after ineligible/eligible costs are calculated.

Footer

Pentucket Regional School District

22 Main Street
West Newbury, MA 01985

Schools

Pentucket Regional High School
24 Main St
West Newbury, MA 01985

Pentucket Regional Middle School
20 Main St
Groveland, MA 01834

  • Facebook
  • Vimeo
  • YouTube

Copyright © 2025 Pentucket Regional School District · Site Design by JGPR